Chinese company paid USD 13.2 million in advance despite failing to reclaim land in Rasmale'

Aug 10, 2026, 8:45 AM
Rasmale'

Rasmale'

It has emerged that China Railway Construction Corporation (CRCC) was paid a USD 13.2 million advance for the reclamation of five sites in Rasmale'—the mega-development project at Fushidhiggaru lagoon—before any physical reclamation work had even commenced.

CRCC was awarded the contract after the government terminated its initial agreement with Capital Marine Engineering Construction (CMC) and decided to divide the reclamation of Rasmale' among multiple contractors. CRCC’s scope included reclaiming 352 hectares of land across sites "A," "B," "H," "I," and "K."

However, the company failed to complete any of the tasks stipulated in the contract as agreed.

Details of the transaction surfaced following a report leaked by the whistleblower account "Hassan Kurusee" on X. The report is an independent evaluation conducted by Epoch Associates for the Housing Development Corporation (HDC), commissioned after CRCC claimed it was owed USD 9.4 million for work performed.

The agreement signed between HDC and CRCC was valued at USD 265.5 million, covering the project from the survey and design phases through to reclamation and coastal protection. The project was divided into three phases, with a total completion timeline of 18 months.

According to documents submitted by CRCC following the agreement, the company claimed to have completed only four percent of the project. Despite this, CRCC’s invoice to HDC demanded USD 6.2 million for preparatory works and USD 3.2 million for reclamation activities.

However, the evaluation by Epoch Associates concluded that CRCC had actually completed only three percent of the total project. The evaluation further revealed that the company had not fully completed a single line item as specified in the contract.

Furthermore, Epoch determined that several tasks CRCC claimed to have finished did not meet the specifications outlined in the contract drawings.

As an example, the report highlighted the construction of a temporary jetty required before the start of major works. CRCC attempted to pass off a small jetty it had reclaimed at Fushidhiggaru lagoon as this structure. However, the jetty did not conform to the designs submitted by the company.

Similarly, CRCC claimed to have largely completed the relocation of coral from Fushidhiggaru lagoon. This was the single most expensive item on their invoice, with the company seeking USD 2.6 million for the task.

But the consultant’s investigation found no evidence of where the corals had been relocated. Epoch noted there was no way to verify whether the relocation had actually taken place and advised against paying for these areas.

The report also indicated that the value of the work completed by CRCC that could actually be utilized by subsequent contractors did not even reach one million dollars.

HDC and CRCC are currently in negotiations to terminate the agreement. During these talks, HDC sought to recover the remaining balance of the USD 13.2 million advance after deducting the value of work performed. However, despite the consultant recommending a much lower valuation in the independent audit, the HDC board agreed to accept the figures proposed by CRCC.

While millions of dollars are being settled with CRCC—a company that failed to reclaim a single hectare of land—HDC completed the entire reclamation of Rasmale' Site "J" for a total cost of USD 21 million.

Comments

Read More

Latest News

Mental health centre opened in Kulhudhuffushi

Kulhudhuffushi City has opened "Manas Hub," a new mental health center launched by the City Council and the Australian High Commissioner. The facility aims to reduce social stigma and provide accessible support, treatment, and early intervention. This milestone marks a major step in strengthening community-based mental health services.

Audit reveals millions in losses over project given to POLCO

An audit revealed millions in losses after the Home Ministry awarded a prison project to POLCO without competitive bidding. POLCO subcontracted the work for a fraction of the price and charged MVR 2.9 million for demolition work that never occurred. The Auditor General has recommended an investigation by the Anti-Corruption Commission.

Yameen urges Eagle Hills to scrap Rasmalé project

Former President Abdulla Yameen has urged Eagle Hills to scrap the Rasmalé project, labeling it an exploitation of a "morally bankrupt" regime. He cited public resentment and controversial lease terms that suggest a permanent loss of land. The project faces heavy criticism for its financial structure and perceived lack of public support.

PG had secured release of suspect detained with film stars

Shahil Mohamed, recently arrested with several film stars for drug offenses, was previously released from pretrial detention in a two-kilogram heroin trafficking case. The Prosecutor General’s Office had requested his release due to his medical condition and length of detention. He has now tested positive for synthetic drugs.

Eagle Hills to develop 5,000 housing units in Urban Isle

UAE’s Eagle Hills will develop 5,000 housing units in Hulhumalé’s "Urban Isle" as a prerequisite for the Rasmalé Waterfront project. The $400–$500 million development features three-bedroom apartments funded by future property sales. This initiative replaces a stalled $8 billion financial center project previously planned for the same site.

Two discharged, two in critical condition after road accident

Two people are in critical condition on ventilators and two others have been discharged following a motorcycle crash in Hulhumalé. The accident occurred when a motorcycle carrying three people fled police by driving against traffic. One victim suffered a brain hemorrhage, and the unlicensed driver reportedly has an extensive criminal record.

Renovation begins at Hulhumale' synthetic track

Renovations have begun on the Hulhumale' synthetic track to upgrade it to international World Athletics standards. The project involves installing a high-quality polyurethane surface to ensure athlete records are officially recognized. Work is expected to be completed by January next year.

Newsletter

Get the latest news delivered straight to your inbox