MVR 56 million wasted through negligence in Fuvahmulah sewerage project

Oct 24, 2023, 9:15 AM
Fuvahmulah City. -- Photo: Mirash Nashim/ Adhadhu

Fuvahmulah City. -- Photo: Mirash Nashim/ Adhadhu

A project to establish water and sewerage services in Fuvahmulah cost MVR 56 million in excess of the budgeted amount due to the actions of successive governments, the Auditor General’s office has said.

The Fuvahmulah water and sewerage project was devised in 2012 with an MVR 160.7 million loan from the Kuwait Fund for Development with the rest to be covered by the state’s Public Sector Investment Program (PSIP) budget. Work began four years later in 2016 and the project was completed in 2019.

According to a performance audit of the project published by the Auditor General’s office, the agreements stated that the project would cost MVR 282.6 million. But a total of MVR 339.9 million was spent due to various problems faced in executing the project.

MVR 20 million extra due to poor coordination

The Fuvahmulah water and sewerage project was carried out under the supervision of the Environment Ministry by a special project management unit.

The Environment Protection Agency (EPA) gave conditional approval to the project’s detailed design report, according to the audit report. In its approval, the EPA asked for revisions to the report with important changes proposed by the EPA along with additional information.

But as a result of the Environment Ministry’s failure to ensure that the revisions were made, measures planned to maintain the project’s quality during the planning, design and execution stages were not implemented, the report stated.

Auditors also flagged four months where no institution coordinated work on the project as well as the failure to properly maintain important documents related to the project. 

Parts of the project’s work were inspected and approved by a party that was not licensed by the Environment Ministry and some parts of the work were not inspected at all.

As a result of these problems, MVR 20.2 million was added to the project’s cost and an additional six months was spent for completion.

Performance certificate issued to contractor despite problems, MVR 43 million to fix

The contractor of the Fuvahmulah water and sewerage project was Sri Lanka’s Sierra Construction company.

According to the audit report, monitoring and evaluation efforts during the defects liability period - which was intended for identifying and resolving problems with the systems - were not properly carried out.

During the period, there was no specific institution for coordinating the project for three months, the audit found, and Fenaka did not participate in its capacity as the system operator during the defects liability period.   

The EPA issued a temporary permit for Fenaka to operate the system on December 13, 2018. But Fenaka was not doing the work at the time. When the issue was noted by the consultant, the Environment Ministry did not take any action apart from sending an email to Fenaka. 

No further action was taken despite the Fuvahmulah City Council informing the Environment Ministry first and then the Planning Ministry later. Despite issuing a permit, the EPA did not take any action or impose a fine on Fenaka over the failure to operate the sewerage system, the audit report noted. 

Leakage of excrement due to the water and sewerage system’s vacuum chambers and manholes filling up was noted during the defects liability period. But the Planning Ministry determined the project to have been completed without instructing the contractor to fix the problems.

An additional MVR 43.2 million needed to be spent to resolve the issues but the audit report noted that the cost should have been borne by the contractor.

Other issues flagged in the audit report:

  • Failure to take action despite setting up a sewage outflow pipe and the vacuum station of the sewage treatment system in an unauthorized area in violation of the environment impact assessment (EIA) report
  • Absence of facilities at Fenaka for adequately operating water and sewerage systems and the lack of adequate efforts to establish such facilities
  • Work on pumping out manholes and vacuum chambers was contracted to a private party without bidding and MVR 8.6 million was spent over 21 months
  • Failure to collect funds due as income and failure to ascertain the cost of operating and maintaining the system due to Fenaka not preparing and submitting a mandatory report on the state of finances
  • Despite the contract stating that the water system could produce 1,500 cubic meters daily, the system could only produce 532 cubic meters.

As corrective measures, the Auditor General’s office recommended strengthening the supervision and monitoring system for such socially and economic important state-funded projects, properly maintaining documentation and regulators taking action through established processes.   

Comments

Read More

Latest News

Mental health centre opened in Kulhudhuffushi

Kulhudhuffushi City has opened "Manas Hub," a new mental health center launched by the City Council and the Australian High Commissioner. The facility aims to reduce social stigma and provide accessible support, treatment, and early intervention. This milestone marks a major step in strengthening community-based mental health services.

Audit reveals millions in losses over project given to POLCO

An audit revealed millions in losses after the Home Ministry awarded a prison project to POLCO without competitive bidding. POLCO subcontracted the work for a fraction of the price and charged MVR 2.9 million for demolition work that never occurred. The Auditor General has recommended an investigation by the Anti-Corruption Commission.

Yameen urges Eagle Hills to scrap Rasmalé project

Former President Abdulla Yameen has urged Eagle Hills to scrap the Rasmalé project, labeling it an exploitation of a "morally bankrupt" regime. He cited public resentment and controversial lease terms that suggest a permanent loss of land. The project faces heavy criticism for its financial structure and perceived lack of public support.

PG had secured release of suspect detained with film stars

Shahil Mohamed, recently arrested with several film stars for drug offenses, was previously released from pretrial detention in a two-kilogram heroin trafficking case. The Prosecutor General’s Office had requested his release due to his medical condition and length of detention. He has now tested positive for synthetic drugs.

Eagle Hills to develop 5,000 housing units in Urban Isle

UAE’s Eagle Hills will develop 5,000 housing units in Hulhumalé’s "Urban Isle" as a prerequisite for the Rasmalé Waterfront project. The $400–$500 million development features three-bedroom apartments funded by future property sales. This initiative replaces a stalled $8 billion financial center project previously planned for the same site.

Two discharged, two in critical condition after road accident

Two people are in critical condition on ventilators and two others have been discharged following a motorcycle crash in Hulhumalé. The accident occurred when a motorcycle carrying three people fled police by driving against traffic. One victim suffered a brain hemorrhage, and the unlicensed driver reportedly has an extensive criminal record.

Renovation begins at Hulhumale' synthetic track

Renovations have begun on the Hulhumale' synthetic track to upgrade it to international World Athletics standards. The project involves installing a high-quality polyurethane surface to ensure athlete records are officially recognized. Work is expected to be completed by January next year.

Newsletter

Get the latest news delivered straight to your inbox