MACL says no section of new terminal will be opened this year after failure to meet deadlines

Nov 27, 2024, 4:46 AM
VIA terminal. -- Photo: Adhadhu

VIA terminal. -- Photo: Adhadhu

Maldives Airports Company Limited (MACL) has announced that no sections of the new terminal at Velana International Airport (VIA) will be inaugurated this year due to failure to meet project deadlines.

MACL first targeted to open the new terminal in September. But due to the slow pace of the project, the company later decided to inaugurate a section of the new terminal in November.

Speaking at a sub-committee of the Parliament Committee on State Owned Enterprises (SOEs), MACL Managing Director Ibrahim Shareef said a section of the terminal can be opened in November if needed.

But he noted that the Airline Operators Committee (AOC), which represents airlines flying to Maldives, had requested that the new terminal not be opened this year in order to avoid problems it may cause with the increase in tourist arrivals from Europe during the winter season.

"One of the reasons these people are saying this. For example, there is a problem here and all the connecting flights from Dubai to Europe will be delayed for one and half hours. They fear a problem like that could happen," he said.

Shareef added that discussions were held with President Dr. Mohamed Muizzu as the new terminal cannot be inaugurated this year as pledged by the President.

85 percent complete, inauguration in June or July

Shareef told the committee that 85 percent of the new terminal is now complete and will be opened in June or July next year.

Work ongoing to complete the new terminal. -- Photo: Adhadhu
Work ongoing to complete the new terminal. -- Photo: Adhadhu

Work ongoing to complete the new terminal. -- Photo: Adhadhu

Before assuming office in November last year, President Muizzu criticized the slow pace of the project and pledged to get it done by September this year.

"The information received in the transition phase shows that the airport will not be completed soon. The current prediction is it will be complete by July 2025. That is not acceptable to us. The economy is slowing down," he said on October 29, 2024.

But his government failed to meet that deadline.

In June this year, Muizzu said the airport would be completed by July 2025. This was the date announced by the former Maldivian Democratic Party (MDP) government as well.

The new passenger terminal is part of the Velana Airport expansion project launched by former President Abdulla Yameen.

The completion of the ongoing expansion project at Velana International Airport, including the passenger terminal, will more than double the airport's capacity to accommodate 7.5 million passengers annually.

The new two-storey terminal will have 78,000 square meters. This will solve the space constraints faced by the existing terminal.

There will also be aero boarding bridges, state-of-the-art baggage handling systems, FNB outlets, lounges and other services

Comments

Read More

Latest News

Mental health centre opened in Kulhudhuffushi

Kulhudhuffushi City has opened "Manas Hub," a new mental health center launched by the City Council and the Australian High Commissioner. The facility aims to reduce social stigma and provide accessible support, treatment, and early intervention. This milestone marks a major step in strengthening community-based mental health services.

Audit reveals millions in losses over project given to POLCO

An audit revealed millions in losses after the Home Ministry awarded a prison project to POLCO without competitive bidding. POLCO subcontracted the work for a fraction of the price and charged MVR 2.9 million for demolition work that never occurred. The Auditor General has recommended an investigation by the Anti-Corruption Commission.

Yameen urges Eagle Hills to scrap Rasmalé project

Former President Abdulla Yameen has urged Eagle Hills to scrap the Rasmalé project, labeling it an exploitation of a "morally bankrupt" regime. He cited public resentment and controversial lease terms that suggest a permanent loss of land. The project faces heavy criticism for its financial structure and perceived lack of public support.

PG had secured release of suspect detained with film stars

Shahil Mohamed, recently arrested with several film stars for drug offenses, was previously released from pretrial detention in a two-kilogram heroin trafficking case. The Prosecutor General’s Office had requested his release due to his medical condition and length of detention. He has now tested positive for synthetic drugs.

Eagle Hills to develop 5,000 housing units in Urban Isle

UAE’s Eagle Hills will develop 5,000 housing units in Hulhumalé’s "Urban Isle" as a prerequisite for the Rasmalé Waterfront project. The $400–$500 million development features three-bedroom apartments funded by future property sales. This initiative replaces a stalled $8 billion financial center project previously planned for the same site.

Two discharged, two in critical condition after road accident

Two people are in critical condition on ventilators and two others have been discharged following a motorcycle crash in Hulhumalé. The accident occurred when a motorcycle carrying three people fled police by driving against traffic. One victim suffered a brain hemorrhage, and the unlicensed driver reportedly has an extensive criminal record.

Renovation begins at Hulhumale' synthetic track

Renovations have begun on the Hulhumale' synthetic track to upgrade it to international World Athletics standards. The project involves installing a high-quality polyurethane surface to ensure athlete records are officially recognized. Work is expected to be completed by January next year.

Newsletter

Get the latest news delivered straight to your inbox