Giraavarufalhu reclamation halts as soaring fuel costs force dredger shutdown

Apr 16, 2026, 10:47 AM
Giravarufalhu reclamation: Work will not be completed by the end of next month --- Photo: MACL

Giravarufalhu reclamation: Work will not be completed by the end of next month --- Photo: MACL

Reclamation work at Giraavarufalhu has come to a halt as Maldives Airports Company Limited (MACL) has ceased providing fuel to the dredgers, contrary to previous agreements.

Information gathered by Adhadhu indicates that the Boskalis dredgers, Oranje and Prins der Nederlanden, which were active in the reclamation project, are currently anchored off Gulhifalhu.

Tracking data from marine traffic websites shows that neither vessel has conducted any reclamation activity over the past 24 hours. However, the exact date the work was halted remains unconfirmed.

A source familiar with the matter, speaking on condition of anonymity, told Adhadhu that the issue stems from rising fuel costs. According to the source, MACL is responsible for financing the fuel for all dredgers utilized in the reclamation projects it oversees.

The location where Boskalis' Prins der Nederlanden was anchored on April 15, 2026 ---- Photo: Marine Traffic
The location where Boskalis' Prins der Nederlanden was anchored on April 15, 2026 ---- Photo: Marine Traffic

The source explained that due to the current spike in fuel prices, the cost of refueling has surged to two or three times the original budget, leading to a decision to "pause briefly."

"The project is ongoing; if it were canceled, the dredgers wouldn't be here. But because fuel expenses have become so high, the dredgers were anchored while discussions take place to decide on the way forward," the source said.

During a parliamentary sitting on Tuesday, Minister of Construction and Infrastructure Abdulla Muththalib stated that the project was handed over to MACL because the previous contractor, Maldives Fund Management Corporation (MFMC), was unable to proceed, leading to significant delays.

MACL is managing the project through its subsidiary, Marine Integrated Infrastructure Development (MIID). Physical reclamation work under the new management commenced on January 31 this year.

By the time MFMC ceased its involvement, 54 hectares had been reclaimed. Muththalib informed Parliament that since MACL took over, an additional 44 hectares were reclaimed as of last Thursday.

"To date, 98 hectares have been reclaimed. It is estimated that the remaining portion of the reclamation will be completed by May 31, 2026," he said. 

This new deadline is two months later than the date previously announced. Prior to the local council elections and the referendum, President Mohamed Muizzu had stated that work would be completed by the end of March, with land plots ready for handover in June.

The location where Boskalis's Oranje was anchored on April 15, 2026 --- Photo: Marine Traffic
The location where Boskalis's Oranje was anchored on April 15, 2026 --- Photo: Marine Traffic

Given that reclamation was not completed by the initial deadline and is now facing further delays, Adhadhu estimates that the project will likely miss the revised date provided by Muththalib as well.

This projection is based on the figures and timelines shared by the Minister with Parliament.

According to Muththalib’s figures, MACL reclaimed 44 hectares over 69 days, averaging 0.6 hectares per day. This is the current output using Boskalis’s two massive dredgers.

At the current rate, it would take 110 days to reclaim the remaining 71 hectares. With only 45 days remaining until the Minister’s projected completion date, the daily reclamation rate would need to increase to 1.5 hectares per day to meet the target.

Based on the actual pace of the Giravarufalhu project, the reclamation phase is more likely to conclude in August. However, with work currently suspended pending a resolution to the fuel issue, there is a high probability that even this timeline may not be met.

Comments

Read More

Latest News

Mental health centre opened in Kulhudhuffushi

Kulhudhuffushi City has opened "Manas Hub," a new mental health center launched by the City Council and the Australian High Commissioner. The facility aims to reduce social stigma and provide accessible support, treatment, and early intervention. This milestone marks a major step in strengthening community-based mental health services.

Audit reveals millions in losses over project given to POLCO

An audit revealed millions in losses after the Home Ministry awarded a prison project to POLCO without competitive bidding. POLCO subcontracted the work for a fraction of the price and charged MVR 2.9 million for demolition work that never occurred. The Auditor General has recommended an investigation by the Anti-Corruption Commission.

Yameen urges Eagle Hills to scrap Rasmalé project

Former President Abdulla Yameen has urged Eagle Hills to scrap the Rasmalé project, labeling it an exploitation of a "morally bankrupt" regime. He cited public resentment and controversial lease terms that suggest a permanent loss of land. The project faces heavy criticism for its financial structure and perceived lack of public support.

PG had secured release of suspect detained with film stars

Shahil Mohamed, recently arrested with several film stars for drug offenses, was previously released from pretrial detention in a two-kilogram heroin trafficking case. The Prosecutor General’s Office had requested his release due to his medical condition and length of detention. He has now tested positive for synthetic drugs.

Eagle Hills to develop 5,000 housing units in Urban Isle

UAE’s Eagle Hills will develop 5,000 housing units in Hulhumalé’s "Urban Isle" as a prerequisite for the Rasmalé Waterfront project. The $400–$500 million development features three-bedroom apartments funded by future property sales. This initiative replaces a stalled $8 billion financial center project previously planned for the same site.

Two discharged, two in critical condition after road accident

Two people are in critical condition on ventilators and two others have been discharged following a motorcycle crash in Hulhumalé. The accident occurred when a motorcycle carrying three people fled police by driving against traffic. One victim suffered a brain hemorrhage, and the unlicensed driver reportedly has an extensive criminal record.

Renovation begins at Hulhumale' synthetic track

Renovations have begun on the Hulhumale' synthetic track to upgrade it to international World Athletics standards. The project involves installing a high-quality polyurethane surface to ensure athlete records are officially recognized. Work is expected to be completed by January next year.

Newsletter

Get the latest news delivered straight to your inbox