Giraavarufalhu reclamation halts as soaring fuel costs force dredger shutdown

Apr 16, 2026, 10:47 AM
Giravarufalhu reclamation: Work will not be completed by the end of next month --- Photo: MACL

Giravarufalhu reclamation: Work will not be completed by the end of next month --- Photo: MACL

Reclamation work at Giraavarufalhu has come to a halt as Maldives Airports Company Limited (MACL) has ceased providing fuel to the dredgers, contrary to previous agreements.

Information gathered by Adhadhu indicates that the Boskalis dredgers, Oranje and Prins der Nederlanden, which were active in the reclamation project, are currently anchored off Gulhifalhu.

Tracking data from marine traffic websites shows that neither vessel has conducted any reclamation activity over the past 24 hours. However, the exact date the work was halted remains unconfirmed.

A source familiar with the matter, speaking on condition of anonymity, told Adhadhu that the issue stems from rising fuel costs. According to the source, MACL is responsible for financing the fuel for all dredgers utilized in the reclamation projects it oversees.

The location where Boskalis' Prins der Nederlanden was anchored on April 15, 2026 ---- Photo: Marine Traffic
The location where Boskalis' Prins der Nederlanden was anchored on April 15, 2026 ---- Photo: Marine Traffic

The source explained that due to the current spike in fuel prices, the cost of refueling has surged to two or three times the original budget, leading to a decision to "pause briefly."

"The project is ongoing; if it were canceled, the dredgers wouldn't be here. But because fuel expenses have become so high, the dredgers were anchored while discussions take place to decide on the way forward," the source said.

During a parliamentary sitting on Tuesday, Minister of Construction and Infrastructure Abdulla Muththalib stated that the project was handed over to MACL because the previous contractor, Maldives Fund Management Corporation (MFMC), was unable to proceed, leading to significant delays.

MACL is managing the project through its subsidiary, Marine Integrated Infrastructure Development (MIID). Physical reclamation work under the new management commenced on January 31 this year.

By the time MFMC ceased its involvement, 54 hectares had been reclaimed. Muththalib informed Parliament that since MACL took over, an additional 44 hectares were reclaimed as of last Thursday.

"To date, 98 hectares have been reclaimed. It is estimated that the remaining portion of the reclamation will be completed by May 31, 2026," he said. 

This new deadline is two months later than the date previously announced. Prior to the local council elections and the referendum, President Mohamed Muizzu had stated that work would be completed by the end of March, with land plots ready for handover in June.

The location where Boskalis's Oranje was anchored on April 15, 2026 --- Photo: Marine Traffic
The location where Boskalis's Oranje was anchored on April 15, 2026 --- Photo: Marine Traffic

Given that reclamation was not completed by the initial deadline and is now facing further delays, Adhadhu estimates that the project will likely miss the revised date provided by Muththalib as well.

This projection is based on the figures and timelines shared by the Minister with Parliament.

According to Muththalib’s figures, MACL reclaimed 44 hectares over 69 days, averaging 0.6 hectares per day. This is the current output using Boskalis’s two massive dredgers.

At the current rate, it would take 110 days to reclaim the remaining 71 hectares. With only 45 days remaining until the Minister’s projected completion date, the daily reclamation rate would need to increase to 1.5 hectares per day to meet the target.

Based on the actual pace of the Giravarufalhu project, the reclamation phase is more likely to conclude in August. However, with work currently suspended pending a resolution to the fuel issue, there is a high probability that even this timeline may not be met.

Comments

Read More

Latest News

Scholars urge government to halt Eagle Hills Rasmalé project

The Scholars’ Union of the Maldives is urging the government to halt the $12 billion Ras Malé project with Eagle Hills. The group claims the deal violates Islamic law and the constitution by potentially allowing non-Muslims to settle permanently. They warn the project could cause irreversible harm to the nation’s religious identity.

Parliament advances Real Estate Bill

The Maldives parliament advanced a bill allowing foreign property buyers to renew 99-year leases indefinitely. By issuing a new lease upon each resale, the law bypasses constitutional limits to boost the real estate market. The bill also formalizes a $12 billion deal with a developer for the Ras Malé project.

Government signs third deal for Ihavandhippolhu

The Maldives government signed a third agreement for the Ihavandhippolhu project, this time with Abu Dhabi’s SAH Group. The deal covers a commercial port and tourism infrastructure for the Maldives Economic Gateway. This follows two previous agreements with foreign firms that have yet to result in any physical work on the site.

Next year’s budget plans no hiring for new posts: Finance

The Maldives finance ministry announced that next year's budget includes no hiring for new positions to ensure economic sustainability. Officials stated that current salaries align with state revenue and that a 10% cap on overtime pay was necessary to prevent debt. No base salaries will be cut under the new pay harmonization framework.

Defamation bill aims to hide government corruption: Fittey

MP Hussain Ziyad criticized a proposed defamation bill, claiming its true purpose is to shield government corruption from public scrutiny. He warned that the bill's vague language and heavy fines, ranging up to MVR 500,000, threaten free speech. Ziyad argued the law mirrors past efforts to suppress reports on government misconduct.

Pension office dismisses COO Shiuna

The Maldives Pension Administration Office dismissed COO Mariyam Shiuna following her suspension in September. Shiuna was reportedly ousted after raising concerns about the chairperson and opposing a government plan to print money through the office. She previously led the Anti-Corruption Commission before joining the agency in 2023.

Defamation bill aims to stifle criticism of Rasmalé deal: Mauroof

MP Mauroof Zakir claims a new defamation bill aims to silence criticism of the Ras Male project and government accountability. The legislation proposes heavy fines and jail time for statements, gestures, or art deemed defamatory. Mauroof argues the bill is a tool to hide corruption and financial mismanagement from public scrutiny.

Newsletter

Get the latest news delivered straight to your inbox