Giraavarufalhu reclamation halts as soaring fuel costs force dredger shutdown

Apr 16, 2026, 10:47 AM
Giravarufalhu reclamation: Work will not be completed by the end of next month --- Photo: MACL

Giravarufalhu reclamation: Work will not be completed by the end of next month --- Photo: MACL

Reclamation work at Giraavarufalhu has come to a halt as Maldives Airports Company Limited (MACL) has ceased providing fuel to the dredgers, contrary to previous agreements.

Information gathered by Adhadhu indicates that the Boskalis dredgers, Oranje and Prins der Nederlanden, which were active in the reclamation project, are currently anchored off Gulhifalhu.

Tracking data from marine traffic websites shows that neither vessel has conducted any reclamation activity over the past 24 hours. However, the exact date the work was halted remains unconfirmed.

A source familiar with the matter, speaking on condition of anonymity, told Adhadhu that the issue stems from rising fuel costs. According to the source, MACL is responsible for financing the fuel for all dredgers utilized in the reclamation projects it oversees.

The location where Boskalis' Prins der Nederlanden was anchored on April 15, 2026 ---- Photo: Marine Traffic
The location where Boskalis' Prins der Nederlanden was anchored on April 15, 2026 ---- Photo: Marine Traffic

The source explained that due to the current spike in fuel prices, the cost of refueling has surged to two or three times the original budget, leading to a decision to "pause briefly."

"The project is ongoing; if it were canceled, the dredgers wouldn't be here. But because fuel expenses have become so high, the dredgers were anchored while discussions take place to decide on the way forward," the source said.

During a parliamentary sitting on Tuesday, Minister of Construction and Infrastructure Abdulla Muththalib stated that the project was handed over to MACL because the previous contractor, Maldives Fund Management Corporation (MFMC), was unable to proceed, leading to significant delays.

MACL is managing the project through its subsidiary, Marine Integrated Infrastructure Development (MIID). Physical reclamation work under the new management commenced on January 31 this year.

By the time MFMC ceased its involvement, 54 hectares had been reclaimed. Muththalib informed Parliament that since MACL took over, an additional 44 hectares were reclaimed as of last Thursday.

"To date, 98 hectares have been reclaimed. It is estimated that the remaining portion of the reclamation will be completed by May 31, 2026," he said. 

This new deadline is two months later than the date previously announced. Prior to the local council elections and the referendum, President Mohamed Muizzu had stated that work would be completed by the end of March, with land plots ready for handover in June.

The location where Boskalis's Oranje was anchored on April 15, 2026 --- Photo: Marine Traffic
The location where Boskalis's Oranje was anchored on April 15, 2026 --- Photo: Marine Traffic

Given that reclamation was not completed by the initial deadline and is now facing further delays, Adhadhu estimates that the project will likely miss the revised date provided by Muththalib as well.

This projection is based on the figures and timelines shared by the Minister with Parliament.

According to Muththalib’s figures, MACL reclaimed 44 hectares over 69 days, averaging 0.6 hectares per day. This is the current output using Boskalis’s two massive dredgers.

At the current rate, it would take 110 days to reclaim the remaining 71 hectares. With only 45 days remaining until the Minister’s projected completion date, the daily reclamation rate would need to increase to 1.5 hectares per day to meet the target.

Based on the actual pace of the Giravarufalhu project, the reclamation phase is more likely to conclude in August. However, with work currently suspended pending a resolution to the fuel issue, there is a high probability that even this timeline may not be met.

Comments

Read More

Latest News

Suspect arrested for repeated public nuisance escapes facility

Ahmed Fairish, a man arrested for public nuisance and harassment, has escaped from a drug treatment facility in Himmafushi. He was transferred there under police supervision following his recent arrest on October 17. Authorities are currently searching for the suspect, who has a history of criminal behavior and making death threats.

PNC secures both seats in election for LGA board

The ruling People’s National Congress (PNC) won both seats in the election for the Local Government Authority board. PNC candidates Ali Ahmed and Maryam Zeena defeated their MDP rivals to represent local councils and Women’s Development Committees. The election occurred alongside the unopposed appointment of Kulhudhuffushi Mayor Mohamed Athif.

"MDP will end Rasmale' deal if it goes without consultation"

MDP Chairperson Fayyaz Ismail warned that a future MDP government will terminate the Rasmalé project if it proceeds without public consultation. He opposes granting land to UAE’s Eagle Hills indefinitely, citing concerns over national sovereignty and the lack of acquisition costs. Fayyaz urged President Muizzu to allow for public debate.

Milestone as Thilamale Bridge connects Villimale and Gulhifalhu

The Thilamale Bridge has reached a major milestone by physically connecting Villimale and Gulhifalhu, creating a continuous link from Male'. Developed by Afcons Infrastructure, the project is now slated for completion in September 2026. Construction progressed through multiple phases despite political disputes over the project's timeline.

Sukuk or bond issue listed in budget for 2027

The government plans to issue a $175 million international bond or sukuk in 2027 to manage foreign debt, part of a $675 million three-year borrowing strategy. Despite past failures to enter the market and a "junk" credit rating, officials hope this move will ease financial pressure following a major reserve drawdown for previous repayments.

Government to deploy an AI-powered smart traffic system in Male'

The Maldives government has included an AI-powered "Smart Traffic Enforcement System" in next year’s budget to tackle congestion in Malé. Part of the "Maldives 2.0" policy, the initiative aims to modernize traffic monitoring through digitalization. The plan also includes a new data center and digital ID system to improve public services.

"President does not have authority to allow non-Muslim residency"

Former Chief Justice Dr. Ahmed Abdulla Didi argues that the President lacks the constitutional authority to grant long-term residency to non-Muslims in Rasmalé. He asserts that such sovereign power belongs solely to the people. Didi also criticized Jamiyyathul Salaf for supporting the government's plan under specific conditions.

Newsletter

Get the latest news delivered straight to your inbox