Rasmale’ reclamation deal with CMCC to be terminated

Jun 2, 2024, 12:04 PM
President Muizzu at Rasmale' project launching. -- Photo: Mirash Nashim/ Adhadhu

President Muizzu at Rasmale' project launching. -- Photo: Mirash Nashim/ Adhadhu

The government has decided to terminate an agreement made with Capital Marine and Construction Company (CMCC) to reclaim land for the development of the Fushidhiggaru lagoon in South Male’ atoll as “Rasmale’.”

At a press conference on Thursday, Construction Minister Dr. Abdulla Muththalib admitted that reclamation work under the government’s flagship project has stalled.

In a post on X after sharing a news article on the subject, the minister said that the government decided not to provide further opportunities when the contractor failed to deliver in line with the agreement. The main reason for this was because the government wanted to carry out the project with financing to be arranged through contractors without awarding land from the Male’ region, he said.

“God willing, work on reclaiming Rasmale’ will begin very soon,” the minister wrote in his post.

Responding to a question from Adhadhu at Thursday’s press conference, Muththalib said the project stalled because CMCC failed to raise finances as proposed by the contractor.

The government previously believed reclamation work would proceed as proposed because there were two dredgers from CMCC’s partner Boskalis in the Maldives at the time, the minister said.

“That’s how they proposed as well. However, when they didn’t carry out work as such, the government is now finding another way,” Muththalib said.

The Housing Development Corporation (HDC) is completing the legal processes for terminating the contract, Adhadhu has learned. However, this is no additional plan at present for carrying out the project.

No funds would be spent from the state budget on the project, which was launched on December 18, 2023, President Dr. Mohamed Muizzu said at the time, after Parliament omitted MVR 400 million allocated for the project in this year’s budget.

Payment for the Rasmale’ project was to be made by awarding 70 hectares of land to the Sri Lankan contractor, including 10 hectares from Hulhumale' and 60 hectares from the land to be reclaimed from the Fushidhiggaru lagoon.

Work on reclaiming 1,153 hectares from the 1,280-hectare lagoon south of Male' with a target of completion in eight months began without an EIA (environment impact assessment) for the whole lagoon. An EIA was only done for the 29-hectare site J.

Aside from about 10 hectares reclaimed from site J in the first week after work began, no other area has been reclaimed to date. But the government previously denied repeatedly that the project had stalled.

Despite President Muizzu saying on the project launch date that land reclamation would be completed without interruption in eight months, the deadline will pass on August 18. The government now says the work will be completed by the end of the year under a new plan.

Comments

Read More

Latest News

Floods affect 85 percent homes, 25 families displaced

Torrential rain in Gaafu Alif Kolamaafushi flooded 85% of homes and displaced 25 families. The MNDF and local council used pumps and drainage channels to restore normalcy after water reached levels of two feet. While streets are now clear, many residents face property damage, power outages, and sewage issues.

Rasmale' residents to get special visa subject to renewal

Foreigners purchasing property in Rasmalé will be eligible for a special residency visa modeled after Malaysia’s "My Second Home" program. Attorney General Ahmed Usham stated the visa will require periodic renewal and follows a separate track from the "Pearl Residency" initiative due to disagreements with developer Eagle Hills.

Alabbar's Israeli ties for Palestinian aid efforts: Usham

Maldives Attorney General Ahmed Usham defended businessman Mohamed Alabbar’s ties to Israel, claiming they are necessary to facilitate humanitarian aid and housing projects for Palestinians. Usham described Alabbar as a transparent person and offered religious scholars the chance to meet him directly to address their concerns.

Customs seizes 3kg of drugs within three days

Maldives Customs seized over 3kg of "Meow Meow" (Synthetic Cathinone) from postal and courier shipments in just three days. These interceptions bring the total amount of the drug seized within a single week to approximately 10kg. Police are currently investigating the cases, though no arrests have been confirmed yet.

Directive against disclosing info of minors in sex abuse cases

The Health Ministry has issued a directive prohibiting the disclosure of any personal information or photos that could identify child victims or offenders. This move aims to safeguard children's dignity and legal rights across all media platforms. The public is reminded that protecting a minor's privacy is a shared legal responsibility.

Heavy rainfall and flooding expected over next four days

The Maldives Met Office warns of heavy rain, thunderstorms, and flooding through November 11 due to an intense southwest monsoon. Several islands have already experienced significant rainfall, prompting a yellow alert for northern atolls. The public is urged to take safety precautions and stay updated on weather alerts.

MACL agreement to pay MVR 1.7 billion for land reclaimed by CMC!

Audit reports reveal MACL agreed to pay MVR 1.76 billion to CMC for land reclamation projects in Hulhumalé, Giraavaru Falhu, and Thilafushi. The secret deal, executed through subsidiary MIID, shifted compensation from land rights to cash payments. Over MVR 1.4 billion of the total settlement is scheduled to be paid within this year.

Newsletter

Get the latest news delivered straight to your inbox