Rasmale' reclamation began without sourcing enough sand: Muththalib

Mar 20, 2024, 9:51 AM
Land reclaimed in Fushidhiggaru lagoon. -- Photo: Mirash Nashim/ Adhadhu

Land reclaimed in Fushidhiggaru lagoon. -- Photo: Mirash Nashim/ Adhadhu

The government's flagship Rasmale' land reclamation project was launched without sourcing enough sand, Construction Minister Dr. Abdulla Muththalib has said.

At a press conference today, Muththalib said the Rasmale' reclamation work began without surveying a large area for sand borrowing. The plan had been to find sand after starting the reclamation, he said.

"However, what they're informing us now is that they need to conduct a more extended sand search campaign because there is not enough sand at the borrow site to continue [the reclamation work]," the minister said.

Despite the Rasmale' reclamation currently not going ahead, the minister said it was not right to say that the work has stalled. Work is ongoing on building the bound wall, he said.

In addition to the lack of sand, as the contractor for the Rasmale' reclamation project, Boskalis, is also reclaiming Gulhifalhu and has brought only one dredger to the Maldives, the minister said the company could only do the Rasmale' reclamation work after completing Gulhifalhu.

"The dredger that Boskalis is using at the moment to reclaim Gulhifalhu, that's only one dredger. They're thinking of moving the dredger after using it to reclaim Gulhifalhu. Because bringing a new dredger would be costly since it's not a project that the state is spending on," Minister Muththalib said.

As a result of the government's efforts to begin the Rasmale' project as soon as possible, Muththalib said the agreement was signed with the contractor without requirements for any advance payments. Therefore, the project would be funded through the sale of land provided to the contractor, he noted.

"So we believe they're thinking of using the dredger here in order to reduce costs. That is the main reason that dredging is not going ahead at the moment," Muththalib said.

This year's budget initially included MVR 400 million allocated for the Rasmale' project. However, after Parliament removed the funds from the budget, the government started the project through the Housing Developing Corporation (HDC).

Work on reclaiming 1,153 hectares from the 1,280-hectare lagoon south of Male' with a target of completion in eight months began without an environment impact assessment (EIA) for the whole lagoon. An EIA was only done for the 29-hectare site J.

The President said reclamation of the massive area would be completed in eight months with the cost to be covered by 70 hectares of land pledged to the Sri Lankan contractor Capital Marine and Construction Company (CMCC), including 10 hectares from Hulhumale' and 60 hectares from the land to be reclaimed from the Fushidhiggaru lagoon.

Comments

Read More

Latest News

Floods affect 85 percent homes, 25 families displaced

Torrential rain in Gaafu Alif Kolamaafushi flooded 85% of homes and displaced 25 families. The MNDF and local council used pumps and drainage channels to restore normalcy after water reached levels of two feet. While streets are now clear, many residents face property damage, power outages, and sewage issues.

Rasmale' residents to get special visa subject to renewal

Foreigners purchasing property in Rasmalé will be eligible for a special residency visa modeled after Malaysia’s "My Second Home" program. Attorney General Ahmed Usham stated the visa will require periodic renewal and follows a separate track from the "Pearl Residency" initiative due to disagreements with developer Eagle Hills.

Alabbar's Israeli ties for Palestinian aid efforts: Usham

Maldives Attorney General Ahmed Usham defended businessman Mohamed Alabbar’s ties to Israel, claiming they are necessary to facilitate humanitarian aid and housing projects for Palestinians. Usham described Alabbar as a transparent person and offered religious scholars the chance to meet him directly to address their concerns.

Customs seizes 3kg of drugs within three days

Maldives Customs seized over 3kg of "Meow Meow" (Synthetic Cathinone) from postal and courier shipments in just three days. These interceptions bring the total amount of the drug seized within a single week to approximately 10kg. Police are currently investigating the cases, though no arrests have been confirmed yet.

Directive against disclosing info of minors in sex abuse cases

The Health Ministry has issued a directive prohibiting the disclosure of any personal information or photos that could identify child victims or offenders. This move aims to safeguard children's dignity and legal rights across all media platforms. The public is reminded that protecting a minor's privacy is a shared legal responsibility.

Heavy rainfall and flooding expected over next four days

The Maldives Met Office warns of heavy rain, thunderstorms, and flooding through November 11 due to an intense southwest monsoon. Several islands have already experienced significant rainfall, prompting a yellow alert for northern atolls. The public is urged to take safety precautions and stay updated on weather alerts.

MACL agreement to pay MVR 1.7 billion for land reclaimed by CMC!

Audit reports reveal MACL agreed to pay MVR 1.76 billion to CMC for land reclamation projects in Hulhumalé, Giraavaru Falhu, and Thilafushi. The secret deal, executed through subsidiary MIID, shifted compensation from land rights to cash payments. Over MVR 1.4 billion of the total settlement is scheduled to be paid within this year.

Newsletter

Get the latest news delivered straight to your inbox