Fushidhiggaru land reclamation stalled, no dredger in sight

Feb 26, 2024, 6:39 AM
President Muizzu at launch of Fushidhiggaru reclamation project.  -- Photo: Mirash Nashim/ Adhadhu

President Muizzu at launch of Fushidhiggaru reclamation project. -- Photo: Mirash Nashim/ Adhadhu

Land reclamation for the current administration's flagship project to develop the Fushidhiggaru lagoon in south Male' atoll as Rasmale' has stalled, Adhadhu has learned.

Aside from 29 hectares at the first reclamation site J, no other area has been reclaimed, photos and videos taken by Adhadhu on February 1 and February 22 showed. A dredger could no longer be seen in the video taken on February 22.

Marine vessel tracking websites confirmed that a dredger was not active in the area. A dredger could not be seen either at the sand borrowing site designated in the EIA (environment impact assessment) report.

When Adhadhu raised questions with the Housing Development Corporation (HDC), which is overseeing the project, a media official said the project was ongoing without any interruption.

Land reclaimed so far under the Rasmale' project. -- Photo: Mirash Nashim/ Adhadhu
Land reclaimed so far under the Rasmale' project. -- Photo: Mirash Nashim/ Adhadhu

Land reclaimed so far under the Rasmale' project. -- Photo: Mirash Nashim/ Adhadhu

However, a credible source with knowledge about the project told Adhadhu that Rasmale' reclamation work has stalled. The source also confirmed that the dredger had left the area.

If work had progressed in line with the schedule in the EIA for the Rasmale' project, the reclamation of site J would have been completed last month by the dredger that started the project.

The timeframe estimated in the EIA for building the bound wall and levelling the ground was between 60 to 75 days. But 69 days have now passed since reclamation of the first stage of Rasmale' began on December 18, 2023. Work progressing in line with the schedule in the EIA can not be seen from the site.

Work on reclaiming 1,153 hectares from the 1,280-hectare lagoon south of Male' with a target of completion in eight months began without an EIA for the whole lagoon. An EIA was only done for the 29-hectare site J.

The President said reclamation of the massive area would be completed in eight months with the cost to be covered by 70 hectares of land pledged to the Sri Lankan contractor Capital Marine and Construction Company (CMCC), including 10 hectares from Hulhumale' and 60 hectares from the land to be reclaimed from the Fushidhiggaru lagoon.

Comments

Read More

Latest News

Floods affect 85 percent homes, 25 families displaced

Torrential rain in Gaafu Alif Kolamaafushi flooded 85% of homes and displaced 25 families. The MNDF and local council used pumps and drainage channels to restore normalcy after water reached levels of two feet. While streets are now clear, many residents face property damage, power outages, and sewage issues.

Rasmale' residents to get special visa subject to renewal

Foreigners purchasing property in Rasmalé will be eligible for a special residency visa modeled after Malaysia’s "My Second Home" program. Attorney General Ahmed Usham stated the visa will require periodic renewal and follows a separate track from the "Pearl Residency" initiative due to disagreements with developer Eagle Hills.

Alabbar's Israeli ties for Palestinian aid efforts: Usham

Maldives Attorney General Ahmed Usham defended businessman Mohamed Alabbar’s ties to Israel, claiming they are necessary to facilitate humanitarian aid and housing projects for Palestinians. Usham described Alabbar as a transparent person and offered religious scholars the chance to meet him directly to address their concerns.

Customs seizes 3kg of drugs within three days

Maldives Customs seized over 3kg of "Meow Meow" (Synthetic Cathinone) from postal and courier shipments in just three days. These interceptions bring the total amount of the drug seized within a single week to approximately 10kg. Police are currently investigating the cases, though no arrests have been confirmed yet.

Directive against disclosing info of minors in sex abuse cases

The Health Ministry has issued a directive prohibiting the disclosure of any personal information or photos that could identify child victims or offenders. This move aims to safeguard children's dignity and legal rights across all media platforms. The public is reminded that protecting a minor's privacy is a shared legal responsibility.

Heavy rainfall and flooding expected over next four days

The Maldives Met Office warns of heavy rain, thunderstorms, and flooding through November 11 due to an intense southwest monsoon. Several islands have already experienced significant rainfall, prompting a yellow alert for northern atolls. The public is urged to take safety precautions and stay updated on weather alerts.

MACL agreement to pay MVR 1.7 billion for land reclaimed by CMC!

Audit reports reveal MACL agreed to pay MVR 1.76 billion to CMC for land reclamation projects in Hulhumalé, Giraavaru Falhu, and Thilafushi. The secret deal, executed through subsidiary MIID, shifted compensation from land rights to cash payments. Over MVR 1.4 billion of the total settlement is scheduled to be paid within this year.

Newsletter

Get the latest news delivered straight to your inbox