Rasmale' city: Only 11 percent reclaimed in 600 days

Aug 17, 2025, 9:32 AM
President Mohamed Muizzu and wife Sajidha Mohamed at the project site. -- Photo: President's Office

President Mohamed Muizzu and wife Sajidha Mohamed at the project site. -- Photo: President's Office

Only 129 hectares of land have been reclaimed 600 days after the government launched its flagship housing project to build Rasmale' city.

The Rasmale' project began on December 18, 2023, with a target to complete the reclamation of Fushidhiggaru lagoon in eight months.

President Mohamed Muizzu announced that 1,153 hectares of land would be reclaimed in the lagoon for the artificial city.

But the Housing Development Corporation (HDC) said through the state broadcaster today that only 129 hectares or 11 percent had been reclaimed so far.

More than 600 days or 20 months have passed since the project began and the dredger had recently stopped work due to pending payments.

The government initially awarded the reclamation work to Capital Marine and Civil Construction (CMCC).

The agreement with CMCC was made with the promise of long-term acquisition of land in exchange for the reclamation.

In eight months, the company reclaimed only 29 hectares. The work stalled and the government decided to cancel the contract.

Satellite image shows Fushidhiggaru lagoon on August 8. -- Photo: Sentinel
Satellite image shows Fushidhiggaru lagoon on August 8. -- Photo: Sentinel

Satellite image shows Fushidhiggaru lagoon on August 8. -- Photo: Sentinel

HDC has now taken a loan and awarded the work to India's Mohan Mutha Exports (MME) and China's China Railway Construction Corporation (CRCC).

The Luxembourg-flagged dredger Francis Beaufort was previously used in the project. About 100 hectares were reclaimed in nine months using the dredger.

Muizzu earlier claimed that the lagoon will be reclaimed in eight months without spending any money from the state budget.

But he has now ordered relevant government agencies to use the state reserves to make advance payments to ensure the project proceeds.

It has also been revealed that the government plans to borrow USD 600 million through three government companies to finance the project.

The President's Office sent a letter to the Finance Ministry requesting arrangements to expedite raising of funds for the project.

According to the letter, the loans will be taken through three government companies to pay the contractors by the Maldives Industrial Development Free Zone (Mid Free Zone).

The President's Office has asked the Finance Ministry to pay the contractor using the state's usable reserves or the currency swap facility provided by India before the loans are settled.

Three loans for Mid Free Zone

  • USD 300 million loan through Greater Male' Financial District Limited
  • USD 200 million loan through Maldives Airports Company Limited
  • USD 100 million loan through State Trading Organisation

The total loan amount is USD 600 million or MVR 9.3 billion.

Construction Minister Abdulla Muththalib earlier said that about USD 500 million to USD 700 million will be spent on reclaiming 1,100 hectares of land in Fushidhiggaru lagoon.

Comments

Read More

Latest News

MDP activist Shamin released from police detention

MDP activist Mohamed Shamin was released from police custody after being detained for allegedly crossing barricades during a protest. The court ruled his actions did not constitute a major felony, noting a lack of evidence for property damage or injury. Shamin still faces charges for obstructing police and disobeying orders.

State will bear no costs on housing units by Abu Dhabi developer

The Maldives Finance Ministry confirmed that the state budget will incur no costs for 5,000 housing units being built by Abu Dhabi’s Eagle Hills. The $500 million project uses a contractor financing model without government guarantees. While the state is not liable, it remains unclear if public recipients will pay for the units upon completion.

Vice President meets UN Secretary-General

Vice President Hussain Mohamed Latheef met UN Secretary-General António Guterres to discuss climate resilience and debt sustainability for the Maldives. The leaders emphasized the urgent need for global climate action and UN reform. They also addressed regional concerns, specifically focusing on the ongoing situation in Palestine.

PNC lawmakers' delegation departs for Pakistan

A 16-member delegation of PNC lawmakers, led by Speaker Abdul Raheem Abdulla, has departed for an exposure visit to Pakistan. The group will visit the Pakistani Parliament and meet with counterparts following an official invitation. This trip precedes a potential, though unconfirmed, upcoming visit by President Mohamed Muizzu.

MDP opens party congress to the public

The Maldivian Democratic Party (MDP) has announced that its upcoming congress, starting October 1 at Male’ City Hall, will be open to the public. While nearly 1,000 official delegates are expected to attend, the party expressed disappointment over the government's refusal to provide a state venue or media coverage for the event.

"Airport was leased to GMR under a transparent bidding process"

Former President Mohamed Nasheed criticized the Maldivian government for awarding a Rasmalé development deal to a UAE firm without a transparent bidding process. He contrasted the secretive agreement with his administration's open tender for the national airport, emphasizing that state assets should only be leased through competitive systems.

What kind of agreement was signed with Eagle Hills

The Maldives government signed a preliminary agreement with UAE-based Eagle Hills to lease land in Rasmalé for 99 years. The multi-billion dollar project aims to develop a world-class marina and luxury residences. While the Maldives will receive 5,000 housing units, specific financial details and a definitive contract are yet to be finalized.