Rasmale' city: Only 11 percent reclaimed in 600 days

Aug 17, 2025, 9:32 AM
President Mohamed Muizzu and wife Sajidha Mohamed at the project site. -- Photo: President's Office

President Mohamed Muizzu and wife Sajidha Mohamed at the project site. -- Photo: President's Office

Only 129 hectares of land have been reclaimed 600 days after the government launched its flagship housing project to build Rasmale' city.

The Rasmale' project began on December 18, 2023, with a target to complete the reclamation of Fushidhiggaru lagoon in eight months.

President Mohamed Muizzu announced that 1,153 hectares of land would be reclaimed in the lagoon for the artificial city.

But the Housing Development Corporation (HDC) said through the state broadcaster today that only 129 hectares or 11 percent had been reclaimed so far.

More than 600 days or 20 months have passed since the project began and the dredger had recently stopped work due to pending payments.

The government initially awarded the reclamation work to Capital Marine and Civil Construction (CMCC).

The agreement with CMCC was made with the promise of long-term acquisition of land in exchange for the reclamation.

In eight months, the company reclaimed only 29 hectares. The work stalled and the government decided to cancel the contract.

Satellite image shows Fushidhiggaru lagoon on August 8. -- Photo: Sentinel
Satellite image shows Fushidhiggaru lagoon on August 8. -- Photo: Sentinel

Satellite image shows Fushidhiggaru lagoon on August 8. -- Photo: Sentinel

HDC has now taken a loan and awarded the work to India's Mohan Mutha Exports (MME) and China's China Railway Construction Corporation (CRCC).

The Luxembourg-flagged dredger Francis Beaufort was previously used in the project. About 100 hectares were reclaimed in nine months using the dredger.

Muizzu earlier claimed that the lagoon will be reclaimed in eight months without spending any money from the state budget.

But he has now ordered relevant government agencies to use the state reserves to make advance payments to ensure the project proceeds.

It has also been revealed that the government plans to borrow USD 600 million through three government companies to finance the project.

The President's Office sent a letter to the Finance Ministry requesting arrangements to expedite raising of funds for the project.

According to the letter, the loans will be taken through three government companies to pay the contractors by the Maldives Industrial Development Free Zone (Mid Free Zone).

The President's Office has asked the Finance Ministry to pay the contractor using the state's usable reserves or the currency swap facility provided by India before the loans are settled.

Three loans for Mid Free Zone

  • USD 300 million loan through Greater Male' Financial District Limited
  • USD 200 million loan through Maldives Airports Company Limited
  • USD 100 million loan through State Trading Organisation

The total loan amount is USD 600 million or MVR 9.3 billion.

Construction Minister Abdulla Muththalib earlier said that about USD 500 million to USD 700 million will be spent on reclaiming 1,100 hectares of land in Fushidhiggaru lagoon.

Comments

Read More

Latest News

Floods affect 85 percent homes, 25 families displaced

Torrential rain in Gaafu Alif Kolamaafushi flooded 85% of homes and displaced 25 families. The MNDF and local council used pumps and drainage channels to restore normalcy after water reached levels of two feet. While streets are now clear, many residents face property damage, power outages, and sewage issues.

Rasmale' residents to get special visa subject to renewal

Foreigners purchasing property in Rasmalé will be eligible for a special residency visa modeled after Malaysia’s "My Second Home" program. Attorney General Ahmed Usham stated the visa will require periodic renewal and follows a separate track from the "Pearl Residency" initiative due to disagreements with developer Eagle Hills.

Alabbar's Israeli ties for Palestinian aid efforts: Usham

Maldives Attorney General Ahmed Usham defended businessman Mohamed Alabbar’s ties to Israel, claiming they are necessary to facilitate humanitarian aid and housing projects for Palestinians. Usham described Alabbar as a transparent person and offered religious scholars the chance to meet him directly to address their concerns.

Customs seizes 3kg of drugs within three days

Maldives Customs seized over 3kg of "Meow Meow" (Synthetic Cathinone) from postal and courier shipments in just three days. These interceptions bring the total amount of the drug seized within a single week to approximately 10kg. Police are currently investigating the cases, though no arrests have been confirmed yet.

Directive against disclosing info of minors in sex abuse cases

The Health Ministry has issued a directive prohibiting the disclosure of any personal information or photos that could identify child victims or offenders. This move aims to safeguard children's dignity and legal rights across all media platforms. The public is reminded that protecting a minor's privacy is a shared legal responsibility.

Heavy rainfall and flooding expected over next four days

The Maldives Met Office warns of heavy rain, thunderstorms, and flooding through November 11 due to an intense southwest monsoon. Several islands have already experienced significant rainfall, prompting a yellow alert for northern atolls. The public is urged to take safety precautions and stay updated on weather alerts.

MACL agreement to pay MVR 1.7 billion for land reclaimed by CMC!

Audit reports reveal MACL agreed to pay MVR 1.76 billion to CMC for land reclamation projects in Hulhumalé, Giraavaru Falhu, and Thilafushi. The secret deal, executed through subsidiary MIID, shifted compensation from land rights to cash payments. Over MVR 1.4 billion of the total settlement is scheduled to be paid within this year.