Land reclamation in Hulhumale' Phase Three suspended again

Sep 8, 2024, 10:10 AM
President Muizzu tours the project site. -- Photo: President's Office

President Muizzu tours the project site. -- Photo: President's Office

Land reclamation in Hulhumale' Phase Three, which began last year under plans to provide land plots to the natives of Male', has been suspended again.

The project was launched after changing the masterplan of Hulhumale' to reclaim a total area of 63 hectares. The project has been suspended many times before.

However, the Housing Development Corporation (HDC) announced in June that the reclamation had resumed.

Comparing photos and videos shared by HDC in June and satellite images taken yesterday, a very small area was reclaimed over the past two months.

That area was reclaimed in the last week of June and the work had been stalled since the end of June.

At the time, HDC said the remaining 40 hectares of the 63 hectares of land would be reclaimed. HDC has not disclosed a reason for suspending the project.

Area to be reclaimed in Phase Three.
Area to be reclaimed in Phase Three.

Area to be reclaimed in Phase Three.

The project was awarded to Capital Marine and Civil Construction Company (CMC) and the reclamation work was handed over to Boskalis of the Netherlands.

Boskalis had been using the dredger Willem van Oranje for the project and the Prins der Nederlanden dredger was brought to the Maldives in April to speed up the work.

However, neither of these dredgers is currently in the Maldives. According to vessel tracking tools, Willem van Oranje is in South Korea while Prins der Nederlanden is in the Philippines.

Satellite image taken yesterday. -- Photo: Sentinel-2
Satellite image taken yesterday. -- Photo: Sentinel-2

Satellite image taken yesterday. -- Photo: Sentinel-2

The reclamation project of Hulhumale' Phase Three was launched on September 22, 2023. The project came to a brief pause and was relaunched by President Dr. Mohamed Muizzu's administration in January.

At the time, political appointees toured the project site and posted photo and video updates on social media. However, the work did not proceed as planned.

The second dredger was brought to speed up the project after resuming the reclamation work.

The project was halted again until June 10 after the Environmental Protection Agency (EPA) ordered the work to be suspended due to coral bleaching.

After that, HDC announced the resumption of work on June 24.

The project, valued at about USD 268 million (MVR 3.9 billion), includes the reclamation of Hulhumale' Phase Three, Dhiyaneru lagoon for a yacht marina and Thilafushi.

The land to be reclaimed in Thilafushi has been awarded to CMC for 99 years with development rights as payment for the project.

The rest of the funding is arranged through a 10-hectare land from Hulhumale' given to CMC for 99 years and a USD 20 million dollar advance.

Comments

Read More

Latest News

Suspect arrested for repeated public nuisance escapes facility

Ahmed Fairish, a man arrested for public nuisance and harassment, has escaped from a drug treatment facility in Himmafushi. He was transferred there under police supervision following his recent arrest on October 17. Authorities are currently searching for the suspect, who has a history of criminal behavior and making death threats.

PNC secures both seats in election for LGA board

The ruling People’s National Congress (PNC) won both seats in the election for the Local Government Authority board. PNC candidates Ali Ahmed and Maryam Zeena defeated their MDP rivals to represent local councils and Women’s Development Committees. The election occurred alongside the unopposed appointment of Kulhudhuffushi Mayor Mohamed Athif.

"MDP will end Rasmale' deal if it goes without consultation"

MDP Chairperson Fayyaz Ismail warned that a future MDP government will terminate the Rasmalé project if it proceeds without public consultation. He opposes granting land to UAE’s Eagle Hills indefinitely, citing concerns over national sovereignty and the lack of acquisition costs. Fayyaz urged President Muizzu to allow for public debate.

Milestone as Thilamale Bridge connects Villimale and Gulhifalhu

The Thilamale Bridge has reached a major milestone by physically connecting Villimale and Gulhifalhu, creating a continuous link from Male'. Developed by Afcons Infrastructure, the project is now slated for completion in September 2026. Construction progressed through multiple phases despite political disputes over the project's timeline.

Sukuk or bond issue listed in budget for 2027

The government plans to issue a $175 million international bond or sukuk in 2027 to manage foreign debt, part of a $675 million three-year borrowing strategy. Despite past failures to enter the market and a "junk" credit rating, officials hope this move will ease financial pressure following a major reserve drawdown for previous repayments.

Government to deploy an AI-powered smart traffic system in Male'

The Maldives government has included an AI-powered "Smart Traffic Enforcement System" in next year’s budget to tackle congestion in Malé. Part of the "Maldives 2.0" policy, the initiative aims to modernize traffic monitoring through digitalization. The plan also includes a new data center and digital ID system to improve public services.

"President does not have authority to allow non-Muslim residency"

Former Chief Justice Dr. Ahmed Abdulla Didi argues that the President lacks the constitutional authority to grant long-term residency to non-Muslims in Rasmalé. He asserts that such sovereign power belongs solely to the people. Didi also criticized Jamiyyathul Salaf for supporting the government's plan under specific conditions.

Newsletter

Get the latest news delivered straight to your inbox