Reclamation has been completed at the Site A of the Hulhumale' phase 3 development, Urbanco announced on Friday.
Hulhumale' phase 3 development is being conducted in two phases. Some 10 hectares of land have now been reclaimed under the first phase.
The second phase of the project will see the reclamation of 53 hectares of land.
Urbanco said in a statement that with the completion of Site A, project work has already started in Site B.
The company has requested that vessels in the area be removed by Tuesday, October 22.
The Hulhumale' phase 3 reclamation project is part of a series of development projects being implemented in the greater Male' region.
The 63-hectare land reclamation project in Hulhumale' Phase 3 will provide a major relief to the housing crisis in the city.