Work on the four-lane expansion of Boduthakurufaanu Magu, running from the Maldives Ports Limited (MPL) area to the Tsunami Monument, will be finished by November, President Mohamed Muizzu has revealed.
In a post on X, Muizzu shared videos and images of the design for the redeveloped section. He said the next phase would be done within four months, along with new wooden jetties for speedboats arriving in the area.
The government says the project is meant to upgrade the city's infrastructure and ease chronic traffic congestion in Male'.
MTCC, the contractor, has already finished the stretch from the Henveiru Ferry Terminal to the North Harbour, at a cost of MVR 144.5 million.
Timeline of the Boduthakurufaanu Magu expansion
9 April 2025: Project awarded to MTCC (Henveiru Ferry Terminal to Local Market).
21 August 2025: Physical work begins on Phase 1 (Segment 1, opposite MMA).
9 December 2025: Segment 1 opens to the public; work begins on Phase 2 (Segment 2, Fish Market to North Harbour).
15 February 2026: Phase 2 (Segment 2) completed and opened to the public.
24 March 2026: Physical work begins on Phase 1 (Segments 2–5, Henveiru Ferry Terminal to Republic Square).
25 July 2026: Phase 1 (Segments 2–5) completed and opened to the public.
MTCC built the project in phases. It finished the section near MMA first, then the stretch between the Fish Market and North Harbour, and finally the run from the Henveiru Ferry Terminal to Republic Square. The whole sequence took 15 months from signing and 11 months from the start of physical work.