Reclamation has begun in the area where land was allocated for housing purposes in Hulhumale' by the previous government.
Urbanco's Managing Director Fazul Rasheed said in a post on X today that the reclamation work has started and guaranteed land for the recipients.
“Those who received land in Hulhumale' will get the plots as promised by President Dr. Muizzu. Without removing a single grain of sand" he wrote.
The reclamation work is now underway for Hulhumale' phase 3, stage 2, site B. The former government had completed reclaiming Site A.
The former government decided to reclaim the land required for the housing from Hulhumale' phase 3.
Sri Lanka's Capital Marine and Civil Construction Company (CMCC) was awarded the contract to reclaim 62.6 hectares of land. However, the work is being carried out by Boskalis of the Netherlands as a sub-contractor.
The company was awarded the land reclamation project in Hulhumale'. Thilafushi and Dhiyaneru lagoon for USD 259 million (MVR 3.98 million).
Hulhumale' phase 3 is being developed as an island separated by channels. Phases 2 and 3 will be connected by four bridges.
CMCC will reclaim the land, put up revetment, ensure shore protection and build the roads, bridges and jetties in Hulhumale' phase 3.